Alberta (AESO)
Week of August 31. Two comment windows close this week, both on Friday.
Corrected November 5, 2026. The first version of this edition named the wrong proposal as leaving the open list and left out a window open to September 11. This version fixes both.
Closing this week
Friday, September 4: comments close on the ISO Tariff Redesign Regulatory Consultation and on Interconnected Electric System Protection Requirements. Two separate consultations, one deadline; a submission held for Monday's coffee still has the week to land.
Coming up
Friday, September 11: feedback closes on Milestone 3 Round 2 of the Reliability Standards Sync Up Project.
What moved
The proposal to amend Section 201.6 has left the open list. It was last tracked as Under Review, and the AESO now lists it as Completed.
The wide view
Alberta's open list stands at 47 items, all tracked. Among them: Locational Marginal Pricing, the 2027 Budget Development Process, the proposed amended definition of “inflexible block” in the ISO Rules, amendments to ID #2012-006R on adequacy, supply shortfall, and energy emergency alerts, and the 2026 Long-Term Outlook Plan, with 42 more behind them.
Independent regulatory analysis by Breaker Brief LLC. Not affiliated with any market operator or regulator. Dates and documents are the source's own. Want the same coverage across several markets, with the weekly written edition? That is the Pro tier.
Reader-supported: paid subscriptions keep Breaker Brief independent and ad-free. Independent regulatory analysis, not legal advice; not affiliated with any market operator or regulator referenced.
Get this in your inbox every Monday